Thursday, June 24, 2010

Vessel is coming together



The deck has been constructed and the two pontoons attached.

We are also currently working on the design of the hydraulic system which will serve to power the oil separator device and run the pumps used to remove the oil from the vessel's oil storage compartments.

Friday, June 18, 2010

Millwright joins the fabrication team



Ralph Hogg has joined our fabrication team. He is a BC Certified Millwright and a CWB 4-Position Welder.





Dan, John and Dave taking a break during a busy day working on the vessel.






We have begun working on the housing for the Oil Separation device.



Friday, June 11, 2010

Pontoons / oil storage compartments nearing completion



The pontoons which also will serve as oil storage compartments with baffles are nearing completion.



Blueprints for the vessel have been submitted to Transport Canada. We are waiting for final approval.

Tuesday, June 1, 2010

Meet the fabrication team


John Dearden, B.S.C, Canadian Institute of Marine Engineering (C.I.M.E.)

Owner of Dearden Marine in Gibsons, B.C., Canada www.deardenmarine.com/





Dan McPherson, Marine Technician, Boat Builder, Sechelt, BC





Fabrication of the prototype vessel has begun. Shown above is the port side pontoon.